Explain During execution, a resource is added to the project team. What effect will this have on the
project?
A. The effect cannot be determined.
B. The project duration will be shortened.
C. A scope change will be required
D. The quality of the project will be increased.

Submitted by: Administrator
A. The effect cannot be determined.