Interviewer And Interviewee Guide

PMI Certification Interview Question:

Explain The senior executive of your company wants monthly schedule update of your project. Which of
the following would you send to the executive?
A. Milestone chart
B. Time-scaled network diagram
C. Arrow activity diagram
D. PERT chart

Submitted by: Administrator
A. Milestone chart
Submitted by: Administrator

Read Online PMI Certification Job Interview Questions And Answers
Copyright 2007-2025 by Interview Questions Answers .ORG All Rights Reserved.
https://InterviewQuestionsAnswers.ORG.