SAP PM Interview Question:
How can we assign measuring points to a strategy plan like compressor running hrs?
Submitted by: AdministratorGo to the change equipment transaction , then extra, then
add or replace counters. then select the desired counter by
F4 help. you can't directly add counters or measuring pts
to a maintenance plan.
u can do this for equipment ,FL and PRT only.
Submitted by: Administrator
add or replace counters. then select the desired counter by
F4 help. you can't directly add counters or measuring pts
to a maintenance plan.
u can do this for equipment ,FL and PRT only.
Submitted by: Administrator