Super Computers Ltd. has 10 staff that spends 40 hours per day making 140 computers. By redesigning their manufacturing process, they increase output to 160 per day. What is the increase in productivity?

Submitted by: Administrator
1. 12.50%
2. 10.87%
3. 20.0%
4. 8.26%
5. 14.29%

14.29%