What is milestone triggering?
Submitted by: AdministratorWhenever the confimation of activities done and if the
milestne is attached with that particular activity the
milstone trigerrs the milstone as per the configuration
done and it will do the nilling through SD module
Submitted by: Administrator
milestne is attached with that particular activity the
milstone trigerrs the milstone as per the configuration
done and it will do the nilling through SD module
Submitted by: Administrator
Milestones can trigger: Billing, scheduling analysis, network/activity creation and release, material component ordering,
Submitted by: Phil