Interviewer And Interviewee Guide

PMI Certification Interview Question:

Explain The PERT method is MOST used in situations where:
A. It is important to know the interrelationships of activities.
B. Little is known about the cost estimated related to the project.
C. Little experience exists on which to base estimated of activity duration.
D. Resource requirements are well defined.

Submitted by: Administrator
C. Little experience exists on which to base estimated of activity duration.
Submitted by: Administrator

Read Online PMI Certification Job Interview Questions And Answers
Copyright 2007-2025 by Interview Questions Answers .ORG All Rights Reserved.
https://InterviewQuestionsAnswers.ORG.