Interviews Certifications Interviews:AFMCAIIMS ExamCCDA CertificationCCIE CertificationCCIP CertificationCCSP CertificationCertificationsCheck Point CertificationCISCO CertificationCIW CertificationEngineering Entrance ExamsEntrance ExamsGATE ExamIBM CertificationICET ExamIIT JEEISTQB CertificationManagement Entrance ExamsMATMCDBA CertificationMCSD.NET - 70-089MCSD.NET - 70-300MCSD.NET - 70-306 ExamMCSD.NET - 70-310 ExamMCSD.NET - 70-315 ExamMCSD.NET - 70-316 ExamMCSD.NET - 70-320 ExamMCSD.NET - 70-330 ExamMCSD.NET - 70-340 ExamMCTS .Net CertificationMedical Science Entrance ExamsMicrosoft CertificationMSCE 2003 CertificationNovell CertificationNovell CLE 9 CertificationNovell CLP CertificationNovell CNA CertificationNovell CNE CertificationNovell MCNE CertificationOCP 9i DBA CertificationOPENMAT ExamOracle Application DeveloperOracle CertificationPMI CertificationPost Graduation Entrance ExamsRed Hat CertificationS/W Quality AssuranceSun CertificationSybase CertificationTesting Certification
Copyright © 2018. All Rights Reserved
PMI Certification Interview Question:
Explain an ideal situation resource leveling should be limited to activities with___?
A. With zero float time.
B. With negative float time.
C. With positive float time.
D. With critical float time
E. On the critical path.
Submitted by: AdministratorC. With positive float time.
Submitted by: Administrator
Submitted by: Administrator
Copyright 2007-2025 by Interview Questions Answers .ORG All Rights Reserved.
https://InterviewQuestionsAnswers.ORG.
https://InterviewQuestionsAnswers.ORG.