Interviews Best Engineering Interviews:Aeronautical EngineeringAgricultural EngineeringApplied EngineeringAssociate EngineeringAutomobile EngineeringBio EngineeringBiomedical EngineerBiomedical EngineeringBuilding Services EngineeringCAD/CAE EngineerChemical EngineeringCivil EngineeringDAE Knitting EngineersDeputy Chief Financial OfficerDesktop EngineerDiesel MechanicElectrical EngineeringElectronics CommunicationsElectronics EngineeringEmbedded Software EngineerEnergy EngineeringEnergy Oil GasEngineeringGalvanizing EngineerIndustrial EngineeringInstrumentation EngineeringLaptop RepairerMachine Learning EngineerMachine OperatorMarine EngineeringMechanical EngineeringMechatronics EngineeringNetwork EngineerNuclear EngineeringPetroleum EngineeringPlant Reliability EngineerPlumberPre EngineeringProduction EngineerRF EngineerSystem EngineeringTextile Engineer
Copyright © 2018. All Rights Reserved
Pre Engineering Interview Question:
Explain me why are pull-out tests performed for soil nails?
Submitted by: MuhammadAd
Pull out tests are performed for primarily the following reasons:
☛ In order to detect and the verification of the bond strength among the soil and the grout adopted during the design of soil nails. This is considered to be as the primary objective of performing pull out tests for soil nails.
☛ For the detection of any slippage or occurrence of creeps.
☛ To detect the elastic and deformations (plastic) of any of the test nails employed. Observations are made during the loading and unloading cycles of the soil nails repetitively.
☛ To achieve the perfect balance the test nails should always be loaded so that the ultimate soil/grout mixture with an upper limit of 80%.
Submitted by: Muhammad
☛ In order to detect and the verification of the bond strength among the soil and the grout adopted during the design of soil nails. This is considered to be as the primary objective of performing pull out tests for soil nails.
☛ For the detection of any slippage or occurrence of creeps.
☛ To detect the elastic and deformations (plastic) of any of the test nails employed. Observations are made during the loading and unloading cycles of the soil nails repetitively.
☛ To achieve the perfect balance the test nails should always be loaded so that the ultimate soil/grout mixture with an upper limit of 80%.