Interviews Construction Job Interviews:ArchitectConstruction LaborConstruction SafetyConstruction WelderDemolition SpecialistDemolition WorkerDemonstrator PromoterDraftsmanEstimatorLeasing ConsultantProduction SupervisorProfessional ArchitectReal Estate AnalystReal Estate BrokerReal Estate DeveloperRigger /Technician
Copyright © 2018. All Rights Reserved
Estimator Interview Question:
What is scheduled performance index (SPI)?
Submitted by: MuhammadThis is a measure of schedule efficiency expressed as the ratio of earned value to planned value. An SPI of 1.0 means that the work actually done so far is exactly the same as the work planned to be done so far. When it is greater than 1.0, project is ahead of schedule meaning more work than planned has been completed and when less than 1.0, it is behind schedule.
Submitted by: Muhammad
Submitted by: Muhammad
Copyright 2007-2024 by Interview Questions Answers .ORG All Rights Reserved.
https://InterviewQuestionsAnswers.ORG.
https://InterviewQuestionsAnswers.ORG.