Interviews Best Management Interviews:Account ManagerAccounts ManagerAdmin PeoplesoftAdministrative AssistantAdministrative OfficerArea ManagerAssistant ManagerAssistant Manager TaxAsst. Operations ManagerBanquet ManagerBrand ManagementBusiness ManagementCash ManagementCity ManagerClub ManagerCost ManagementCustomer Relationship Manager(CRM)Deputy General Manager(DGM)Deputy Manager SecurityEffective Leadership SkillsEmployee Reference CheckERP OperationsExecutive AssistantFactory ManagerFailure PreventionFinancial ManagementGeneral Manager (GM)GM ProcessingGood Effective ManagementGood Team LeaderGoods Dispatch ExectiveHospital ManagerHotel ManagementHuman Resource (HR)Industrial ManagementInformation Technology ManagementInfrastructure ManagementInternal Audit and Cost ManagerLeadership SkillsLeading TeamLogistic CoordinatorManagementManagement ConsultingManagement ExecutiveManagement SkillsManagement StyleManager BakeryManager Call CenterManager ConstructionManager ContractsManager Garments DepartmentManager ImportsManager ProcurementManager SkillsManager StoresManager SustainabilityMBANon TechnicalNurse ManagerOffice ManagerOffice Support AssistantOperation ManagerOperations CoordinatorOperations ManagementOperations strategyPeoplesoftPersonnel ManagementProduct ManagerProduct Packing ManagerProduction ManagerProject CoordinatorProject ManagementProject Management Professional (PMP)Project ManagerRecord ManagerResearch Media ManagerRetail ManagementRetail ManagerSalary ExpectationsSenior Project OfficerSix SigmaStore KeeperStore SupervisorSupervisorSupply Chain OfficerTeam LeadTechnical ManagerTechnical Project ManagerTest ManagerTime ManagementTraining ManagerUnit Manager
Copyright © 2018. All Rights Reserved
Cost Management Interview Question:
Although the stakeholders thought there was enough money in the budget, halfway through the project the cost performance index (CPI) is 0.7. To determine the root cause, several stakeholders audit the project and discover the project cost budget was estimated analogously. Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the estimate was campleted. Which of the following describes what was missing?
A. Estimated costs should be used to measure CPI
B. SPI should be used, not CPI
C. Bottom-up estimating should have been used
D. Past history was not taken into account
Submitted by: AdministratorC. Bottom-up estimating should have been used