Cost Management Interview Question:

Estimate at completion (EAC) is a periodic evaluation of:

A. The cost of work completed
B. The value of work performed
C. The anticipated total cost at project completion
D. What it will cost to finish the job

Submitted by: Murtaza
C. The anticipated total cost at project completion
Submitted by: Murtaza