Interviews Best Management Interviews:Account ManagerAccounts ManagerAdmin PeoplesoftAdministrative AssistantAdministrative OfficerArea ManagerAssistant ManagerAssistant Manager TaxAsst. Operations ManagerBanquet ManagerBrand ManagementBusiness ManagementCash ManagementCity ManagerClub ManagerCost ManagementCustomer Relationship Manager(CRM)Deputy General Manager(DGM)Deputy Manager SecurityEffective Leadership SkillsEmployee Reference CheckERP OperationsExecutive AssistantFactory ManagerFailure PreventionFinancial ManagementGeneral Manager (GM)GM ProcessingGood Effective ManagementGood Team LeaderGoods Dispatch ExectiveHospital ManagerHotel ManagementHuman Resource (HR)Industrial ManagementInformation Technology ManagementInfrastructure ManagementInternal Audit and Cost ManagerLeadership SkillsLeading TeamLogistic CoordinatorManagementManagement ConsultingManagement ExecutiveManagement SkillsManagement StyleManager BakeryManager Call CenterManager ConstructionManager ContractsManager Garments DepartmentManager ImportsManager ProcurementManager SkillsManager StoresManager SustainabilityMBANon TechnicalNurse ManagerOffice ManagerOffice Support AssistantOperation ManagerOperations CoordinatorOperations ManagementOperations strategyPeoplesoftPersonnel ManagementProduct ManagerProduct Packing ManagerProduction ManagerProject CoordinatorProject ManagementProject Management Professional (PMP)Project ManagerRecord ManagerResearch Media ManagerRetail ManagementRetail ManagerSalary ExpectationsSenior Project OfficerSix SigmaStore KeeperStore SupervisorSupervisorSupply Chain OfficerTeam LeadTechnical ManagerTechnical Project ManagerTest ManagerTime ManagementTraining ManagerUnit Manager
Copyright © 2018. All Rights Reserved
Manager Construction Interview Question:
Pick up incorrect statement from following:
A. An activity of a project is denoted by an arrow on the net work
B. The tail of the arrow indicates the start of the activity
C. The head of the arrow indicates the end of the activity
D. The arrows are drawn to scale from left to right
E. Each activity consumes a given time
Submitted by: AdministratorD. The arrows are drawn to scale from left to right