Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:
A:
1. Pouring of Concrete
2. Erection of form work
3. Curing of concrete
4. Removal of form work

B:
1. Erection of form work
2. Pouring of concrete
3. Curing of concrete
4. Removal of form work

C:
1. Removal of form work
2. Erection of form work
3. Pouring of concrete
4. Curing of concrete

D:
1. Pouring of concrete
2. Curing of concrete
3. Erection of form work
4. Removal of form work

Submitted by: Administrator
D:
1. Pouring of concrete
2. Curing of concrete
3. Erection of form work
4. Removal of form work