Interviewer And Interviewee Guide
Interviews Quizzes

Cost Management Interview Question:

A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91. Generally, what is the BEST explanation for why this occurred?

A. The scope was changed
B. A supplier went out of business and a new one needed to be found
C. Additional equipment needed to be purchased
D. A critical path activity took longer and needed more labor hours to complete

Submitted by: Administrator
D. A critical path activity took longer and needed more labor hours to complete
Submitted by:

Read Online Cost Management Job Interview Questions And Answers
Copyright 2007-2024 by Interview Questions Answers .ORG All Rights Reserved.
https://InterviewQuestionsAnswers.ORG.