Interviews Best Management Interviews:Account ManagerAccounts ManagerAdmin PeoplesoftAdministrative AssistantAdministrative OfficerArea ManagerAssistant ManagerAssistant Manager TaxAsst. Operations ManagerBanquet ManagerBrand ManagementBusiness ManagementCash ManagementCity ManagerClub ManagerCost ManagementCustomer Relationship Manager(CRM)Deputy General Manager(DGM)Deputy Manager SecurityEffective Leadership SkillsEmployee Reference CheckERP OperationsExecutive AssistantFactory ManagerFailure PreventionFinancial ManagementGeneral Manager (GM)GM ProcessingGood Effective ManagementGood Team LeaderGoods Dispatch ExectiveHospital ManagerHotel ManagementHuman Resource (HR)Industrial ManagementInformation Technology ManagementInfrastructure ManagementInternal Audit and Cost ManagerLeadership SkillsLeading TeamLogistic CoordinatorManagementManagement ConsultingManagement ExecutiveManagement SkillsManagement StyleManager BakeryManager Call CenterManager ConstructionManager ContractsManager Garments DepartmentManager ImportsManager ProcurementManager SkillsManager StoresManager SustainabilityMBANon TechnicalNurse ManagerOffice ManagerOffice Support AssistantOperation ManagerOperations CoordinatorOperations ManagementOperations strategyPeoplesoftPersonnel ManagementProduct ManagerProduct Packing ManagerProduction ManagerProject CoordinatorProject ManagementProject Management Professional (PMP)Project ManagerRecord ManagerResearch Media ManagerRetail ManagementRetail ManagerSalary ExpectationsSenior Project OfficerSix SigmaStore KeeperStore SupervisorSupervisorSupply Chain OfficerTeam LeadTechnical ManagerTechnical Project ManagerTest ManagerTime ManagementTraining ManagerUnit Manager
Copyright © 2018. All Rights Reserved
Cost Management Interview Question:
The customer responsible for overseeing your project asks you to provide a written cost estimate that is 30 percent higher than your estimate of the project's cost. He explains that the budgeting process requires managers to estimate pessimistically to ensure enough money is allocated for projects. What is the BEST way to handle this?
A. Add the 30 percent as a lump sum contingency fund to handle project risks
B. Add the 30 percent to your cost estimate by spreading it evenly across all project activities
C. Create one cost baseline for budget allocation and a second one for the actual project management plan
D. Ask for information on risks that would cause your estimate to be too low
Submitted by: MurtazaD. Ask for information on risks that would cause your estimate to be too low
Submitted by: Murtaza
Submitted by: Murtaza