Cost Management Interview Question:

A new store development project requires the purchase of various equipment, machinery, and furniture. The department responsible for the development recently centralized its external purchasing process and standardized its new order system. In which document can these new procedures be found?

A. Project scope statement
B. WBS
C. Staffing management plan
D. Organizational policies

Submitted by: Administrator
D. Organizational policies