Interviews Best Management Interviews:Account ManagerAccounts ManagerAdmin PeoplesoftAdministrative AssistantAdministrative OfficerArea ManagerAssistant ManagerAssistant Manager TaxAsst. Operations ManagerBanquet ManagerBrand ManagementBusiness ManagementCash ManagementCity ManagerClub ManagerCost ManagementCustomer Relationship Manager(CRM)Deputy General Manager(DGM)Deputy Manager SecurityEffective Leadership SkillsEmployee Reference CheckERP OperationsExecutive AssistantFactory ManagerFailure PreventionFinancial ManagementGeneral Manager (GM)GM ProcessingGood Effective ManagementGood Team LeaderGoods Dispatch ExectiveHospital ManagerHotel ManagementHuman Resource (HR)Industrial ManagementInformation Technology ManagementInfrastructure ManagementInternal Audit and Cost ManagerLeadership SkillsLeading TeamLogistic CoordinatorManagementManagement ConsultingManagement ExecutiveManagement SkillsManagement StyleManager BakeryManager Call CenterManager ConstructionManager ContractsManager Garments DepartmentManager ImportsManager ProcurementManager SkillsManager StoresManager SustainabilityMBANon TechnicalNurse ManagerOffice ManagerOffice Support AssistantOperation ManagerOperations CoordinatorOperations ManagementOperations strategyPeoplesoftPersonnel ManagementProduct ManagerProduct Packing ManagerProduction ManagerProject CoordinatorProject ManagementProject Management Professional (PMP)Project ManagerRecord ManagerResearch Media ManagerRetail ManagementRetail ManagerSalary ExpectationsSenior Project OfficerSix SigmaStore KeeperStore SupervisorSupervisorSupply Chain OfficerTeam LeadTechnical ManagerTechnical Project ManagerTest ManagerTime ManagementTraining ManagerUnit Manager
Copyright © 2018. All Rights Reserved
Cost Management Interview Question:
Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?
A. Eliminate risks in estimates and reestimate
B. Meet with the sponsor to find out what work can be done sooner
C. Cut quality
D. Decrease scope
Submitted by: AdministratorA. Eliminate risks in estimates and reestimate