Cost Management Interview Question:

The cost contingency reserve should be:

A. Hidden to prevent management from disallowing the reserve
B. Added to each activity to provide the customer with a shorter critical path
C. Maintained by management to cover cost overruns
D. Added to the base costs of the project to account for risks

Submitted by: Administrator
D. Added to the base costs of the project to account for risks