Interviews Best Management Interviews:Account ManagerAccounts ManagerAdmin PeoplesoftAdministrative AssistantAdministrative OfficerArea ManagerAssistant ManagerAssistant Manager TaxAsst. Operations ManagerBanquet ManagerBrand ManagementBusiness ManagementCash ManagementCity ManagerClub ManagerCost ManagementCustomer Relationship Manager(CRM)Deputy General Manager(DGM)Deputy Manager SecurityEffective Leadership SkillsEmployee Reference CheckERP OperationsExecutive AssistantFactory ManagerFailure PreventionFinancial ManagementGeneral Manager (GM)GM ProcessingGood Effective ManagementGood Team LeaderGoods Dispatch ExectiveHospital ManagerHotel ManagementHuman Resource (HR)Industrial ManagementInformation Technology ManagementInfrastructure ManagementInternal Audit and Cost ManagerLeadership SkillsLeading TeamLogistic CoordinatorManagementManagement ConsultingManagement ExecutiveManagement SkillsManagement StyleManager BakeryManager Call CenterManager ConstructionManager ContractsManager Garments DepartmentManager ImportsManager ProcurementManager SkillsManager StoresManager SustainabilityMBANon TechnicalNurse ManagerOffice ManagerOffice Support AssistantOperation ManagerOperations CoordinatorOperations ManagementOperations strategyPeoplesoftPersonnel ManagementProduct ManagerProduct Packing ManagerProduction ManagerProject CoordinatorProject ManagementProject Management Professional (PMP)Project ManagerRecord ManagerResearch Media ManagerRetail ManagementRetail ManagerSalary ExpectationsSenior Project OfficerSix SigmaStore KeeperStore SupervisorSupervisorSupply Chain OfficerTeam LeadTechnical ManagerTechnical Project ManagerTest ManagerTime ManagementTraining ManagerUnit Manager
Copyright © 2018. All Rights Reserved
Cost Management Interview Question:
Your project has a medium amount of risk and is not very well defined. The sponsor hands you a project charter and asks you to confirm that the project can be completed within the project cost budget. What is the BEST method to handle this?
A. Build the estimate in the form of a range of possible results
B. Ask the team members to help estimate the cost based on the project charter
C. Based on the information you have, calculate a parametric estimate
D. Provide an analogous estimate based on past history.
Submitted by: AdministratorA. Build the estimate in the form of a range of possible results