It's observed that the testers in your organization are performing tests on the deliverable even after significant defects have been found. This has resulted in unnecessary testing of little value because re-testing needs to be done after defects have been rectified. You are the test manager and going to update the test plan with recommendations on when to stop testing. List the recommendations you are going to make?

Submitted by: Administrator
Following steps need to be taken .
a) Acceptance criteria should tighten
b) Test cases should be re-evaluated (preferably peer review)
c) If possible more test cases should be added. With boundary value and
equivalence class partition cases.
d) More test cases with invalid condition should be added
e) Stop criteria needs to be modified
Submitted by: Administrator