Explain The senior executive of your company wants monthly schedule update of your project. Which of
the following would you send to the executive?
A. Milestone chart
B. Time-scaled network diagram
C. Arrow activity diagram
D. PERT chart

Submitted by: Administrator
A. Milestone chart
Submitted by: Administrator