How to schedule counter base maintenance plant for DG in power plant that need 800hr per month maint this steps i followed.
1)i have created meas pt with counter (IK01) created meas
document IK11 then schedule thru IP10.
but not getting due order list in ip24
Submitted by: AdministratorFirst of all, you cannot get 800 hrs per month...
For counter based... it will schedule in two days... like..
days and hours... but.. if u schedule in IP10..it wil take
the annual reading and schedule the dates.. So.. if the
running hrs didn't reach, but the date reached... so.. it
will open a order...
Give the annual reading according to the running hrs of the
DG.. then u will get
Submitted by: Administrator
For counter based... it will schedule in two days... like..
days and hours... but.. if u schedule in IP10..it wil take
the annual reading and schedule the dates.. So.. if the
running hrs didn't reach, but the date reached... so.. it
will open a order...
Give the annual reading according to the running hrs of the
DG.. then u will get
Submitted by: Administrator
Read Online SAP PM Job Interview Questions And Answers
Top SAP PM Questions
☺ | What are the common PM interview questions? |
☺ | What is meant by single cycle plan ?how it works? |
☺ | How to add the counter plan and strategy plan in a single maintenance plan? |
☺ | How can we assign measuring points to a strategy plan like compressor running hrs? |
☺ | What is refurbishment order? Explain the total cycle? |
Top ERP Categories
☺ | SAP Basis Interview Questions. |
☺ | SAP SD Interview Questions. |
☺ | SAP MM Interview Questions. |
☺ | SAP ALE IDocs Interview Questions. |
☺ | SAP PP Interview Questions. |