Pick up correct statement from the following:
A. The float may be positive, zero or negative
B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
D. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
E. All the above.
Submitted by: AdministratorE. All the above
Submitted by:
Submitted by:
Read Online Payables Management Job Interview Questions And Answers
Top Payables Management Questions
☺ | Most popular type of organisation used for Civil Engineering Constructions, is: |
☺ | Estimated time required to perform an activity, is known as: |
☺ | The Time and progress chart of a construction, is also known as: |
☺ | Performance of a specific task in CPM, is known: |
☺ | Artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as: |
Top Business and Economics Categories
☺ | Taxation Interview Questions. |
☺ | Economics Interview Questions. |
☺ | Accounts Receivable (AR) Interview Questions. |
☺ | General Ledger Interview Questions. |
☺ | Fixed Assets Interview Questions. |