Annual requirements contract to deliver file cabinets each month was issued. The contract did not say anything about who bears cost of uncrating and setting up cabinets in offices. The supplier has uncrated and set up cabinets first four months of contract. Now, supplier is refusing to uncrate and set up cabinets unless he can increase his price. Can I force supplier to continue to uncrate and set up cabinets in offices at same contract price?

Submitted by: Administrator
The supplier has to uncrate and set up the cabinets at no additional cost as the supplier has shown by course of his performance during the first four months of the contract that his intention was to uncrate and set up the cabinets.