Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:
A:
1. Pouring of Concrete
2. Erection of form work
3. Curing of concrete
4. Removal of form work
B:
1. Erection of form work
2. Pouring of concrete
3. Curing of concrete
4. Removal of form work
C:
1. Removal of form work
2. Erection of form work
3. Pouring of concrete
4. Curing of concrete
D:
1. Pouring of concrete
2. Curing of concrete
3. Erection of form work
4. Removal of form work
Submitted by: AdministratorD:
1. Pouring of concrete
2. Curing of concrete
3. Erection of form work
4. Removal of form work
Submitted by:
1. Pouring of concrete
2. Curing of concrete
3. Erection of form work
4. Removal of form work
Submitted by:
Read Online Management Job Interview Questions And Answers
Top Management Questions
☺ | The first method invented for planning projects, was: |
☺ | Site order book is used for recording: |
☺ | Final technical authority of a project lies with: |
☺ | The performance of a specific task in CPM, is known: |
☺ | Time and progress chart of a construction, is also known as: |
Top Best Management Categories
☺ | Store Keeper Interview Questions. |
☺ | Administrative Officer Interview Questions. |
☺ | Good Team Leader Interview Questions. |
☺ | Hotel Management Interview Questions. |
☺ | Project Coordinator Interview Questions. |