Pick up the incorrect statement from the following:
A. An activity of a project is denoted by an arrow on the net work
B. The tail of the arrow indicates the start of the activity
C. The head of the arrow indicates the end of the activity
D. The arrows are drawn to scale from left to right
E. Each activity consumes a given time
Submitted by: AdministratorD. The arrows are drawn to scale from left to right
Submitted by:
Submitted by:
Read Online Management Job Interview Questions And Answers
Top Management Questions
☺ | The first method invented for planning projects, was: |
☺ | Site order book is used for recording: |
☺ | Final technical authority of a project lies with: |
☺ | The performance of a specific task in CPM, is known: |
☺ | Time and progress chart of a construction, is also known as: |
Top Best Management Categories
☺ | Store Keeper Interview Questions. |
☺ | Administrative Officer Interview Questions. |
☺ | Good Team Leader Interview Questions. |
☺ | Hotel Management Interview Questions. |
☺ | Project Coordinator Interview Questions. |