Pick up the incorrect statement from the following:
A. The activity is the time consuming part of a project
B. The beginning and end of a job, are called events
C. The activity which consumes maximum time, is called a node
D. Logically and sequentially connected activities and events form a network
E. None of these

Submitted by: Administrator
C. The activity which consumes maximum time, is called a node
Submitted by:

Read Online Management Job Interview Questions And Answers