All of the following are outputs of the Estimate Costs process EXCEPT:
A. An understanding of the cost risk in the work that has been estimated
B. The prevention of inappropriate changes from being induded in the cost baseline
C. An indication of the range of possible costs for the project
D. Documentation of any assumptions made during the Estimate Costs process
Submitted by: AdministratorB. The prevention of inappropriate changes from being induded in the cost baseline
Submitted by:
Submitted by:
Read Online Cost Management Job Interview Questions And Answers
Top Cost Management Questions
☺ | Which type of cost is team training? |
☺ | During which project management process group are budget forecasts created? |
☺ | Project setup costs are an example of: |
☺ | Value analysis is performed to get: |
Top Best Management Categories
☺ | Store Keeper Interview Questions. |
☺ | Administrative Officer Interview Questions. |
☺ | Good Team Leader Interview Questions. |
☺ | Hotel Management Interview Questions. |
☺ | Project Coordinator Interview Questions. |