You have been asked to select between three projects. Project A has a net present value of $54,750 and will take six months to complete. Project B has a net present value of $85,100 and will take two years to complete. Project C has a net present value or $15,000 and a benefit-cost ratio of 5:2. Which project should you choose?
A. Project A
B. Project B
C. Project C
D. There is not enough information to decide.
Submitted by: AdministratorB. Project B
Submitted by:
Submitted by:
Read Online Cost Management Job Interview Questions And Answers
Top Cost Management Questions
☺ | Which type of cost is team training? |
☺ | During which project management process group are budget forecasts created? |
☺ | Project setup costs are an example of: |
☺ | Value analysis is performed to get: |
Top Best Management Categories
☺ | Store Keeper Interview Questions. |
☺ | Administrative Officer Interview Questions. |
☺ | Good Team Leader Interview Questions. |
☺ | Hotel Management Interview Questions. |
☺ | Project Coordinator Interview Questions. |