Pick up incorrect statement from following:
A. An activity of a project is denoted by an arrow on the net work
B. The tail of the arrow indicates the start of the activity
C. The head of the arrow indicates the end of the activity
D. The arrows are drawn to scale from left to right
E. Each activity consumes a given time
Submitted by: AdministratorD. The arrows are drawn to scale from left to right
Submitted by:
Submitted by:
Read Online Manager Construction Job Interview Questions And Answers
Top Manager Construction Questions
☺ | Time and progress chart of construction, is also known as: |
☺ | Performance of specific task in CPM, is known: |
☺ | The Mile Stone charts were invented in year of: |
☺ | The Various activities of project, are shown on bar charts by: |
Top Best Management Categories
☺ | Store Keeper Interview Questions. |
☺ | Administrative Officer Interview Questions. |
☺ | Good Team Leader Interview Questions. |
☺ | Hotel Management Interview Questions. |
☺ | Project Coordinator Interview Questions. |