Suppose if D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good:

A. EF = ES + D
B. LS = LF - D
C. LF = LS + D
D. D = EF - ES
E. all the above.

Submitted by: Administrator
E. all the above.