The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this?

A. Cost Management
B. Estimate Costs
C. Determine Budget
D. Control Costs

Submitted by: Administrator
C. Determine Budget
Submitted by:

Read Online Cost Management Job Interview Questions And Answers