The seller tells you that your activities have resulted in an increase in their costs. You should:
A. Recommend a change to the project costs
B. Have a meeting with management to find out what to do
C. Ask the seller for supporting information
D. Deny any wrongdoing
Submitted by: AdministratorC. Ask the seller for supporting information