Which of the following is NOT needed in order to come up with a project estimate?
A. A WBS
B. A network diagram
C. Risks
D. A change control system
Submitted by: AdministratorD. A change control system
Submitted by:
Submitted by:
Read Online Cost Management Job Interview Questions And Answers