You have just completed the initiating processes of a small project and are moving into the planning processes when a project stakeholder asks you for the projects budget and cost baseline. What should you tell her?
A. The project budget can be found in the project's charter, which has just been completed
B. The project budget and baseline will not be finalized and accepted until the planning processes are completed
C. The project management plan will not contain the project's budget and baseline; this is a small project
D. It is impossible to complete an estimate before the project management plan is created
Submitted by: AdministratorB. The project budget and baseline will not be finalized and accepted until the planning processes are completed
Submitted by:
Submitted by:
Read Online Cost Management Job Interview Questions And Answers
Top Cost Management Questions
☺ | Which type of cost is team training? |
☺ | During which project management process group are budget forecasts created? |
☺ | Project setup costs are an example of: |
☺ | Value analysis is performed to get: |
Top Best Management Categories
☺ | Store Keeper Interview Questions. |
☺ | Administrative Officer Interview Questions. |
☺ | Good Team Leader Interview Questions. |
☺ | Hotel Management Interview Questions. |
☺ | Project Coordinator Interview Questions. |