Your project has a medium amount of risk and is not very well defined. The sponsor hands you a project charter and asks you to confirm that the project can be completed within the project cost budget. What is the BEST method to handle this?
A. Build the estimate in the form of a range of possible results
B. Ask the team members to help estimate the cost based on the project charter
C. Based on the information you have, calculate a parametric estimate
D. Provide an analogous estimate based on past history.
Submitted by: AdministratorA. Build the estimate in the form of a range of possible results
Submitted by:
Submitted by:
Read Online Cost Management Job Interview Questions And Answers
Top Cost Management Questions
☺ | Which type of cost is team training? |
☺ | During which project management process group are budget forecasts created? |
☺ | Project setup costs are an example of: |
☺ | Value analysis is performed to get: |
Top Best Management Categories
☺ | Store Keeper Interview Questions. |
☺ | Administrative Officer Interview Questions. |
☺ | Good Team Leader Interview Questions. |
☺ | Hotel Management Interview Questions. |
☺ | Project Coordinator Interview Questions. |