A project manager needs to analyze the project costs to find ways to decrease costs. It would be BEST if the project manager looks at:

A. Variable costs and fixed costs
B. Fixed costs and indirect costs
C. Direct costs and variable costs
D. Indirect costs and direct costs

Submitted by: Administrator
C. Direct costs and variable costs