Cost risk means:

A. There are risks that will cost the project money
B. The project is too risky from a cost aspect
C. There is a risk that project costs could go higher than planned
D. There is a risk that the cost of the project will be lower than planned

Submitted by: Administrator
C. There is a risk that project costs could go higher than planned