You are managing a construction project that is currently being initiated. You met with the sponsors and several important stakeholders, and have started to work on the preliminary scope statement. You've documented several key assumptions that have been made, and identified project constraints and initial risks. Before you can finish the preliminary scope statement, you must make a rough order of magnitude estimate of both time and cost so that the sponsor can allocate the final budget.

What is the range of a rough order of magnitude (ROM) estimate?

A. -10% to +10%
B. -50% to +50%
C. -50% to +100%
D. -100% to +200%

Submitted by: Administrator
C. -50% to +100%