You are managing a construction project to install new door frames in an office building. You planned on spending $12,500 on the project, but your costs are higher than expected, and now you're afraid that your project is spending too much money. What number tells you the difference between the amount of money you planned on spending and what you've actually spent so far on the project?
A. AC
B. SV
C. CV
D. VAC
Submitted by: Administrator
C. CV
Submitted by:
Read Online Cost Management Job Interview Questions And Answers