You are managing a project with AC = $25,100 , ETC = $45,600 , VAC = -$2,600, BAC = $90,000, and EAC = $92,100. Your sponsor asks you to forecast how much money you expect to spend on the remainder of the project. Which is the BEST estimate to use for this forecast?
A. $45,600
B. $87,400
C. $90,000
D. $92,100
Submitted by: AdministratorA. $45,600